March Update


March has had a main focus upon preparation as well as health and safety, making the site as safe as possible and putting the correct signage in place as well as all staff involved from Yorkshire Water and Black and Veatch having taken part in safety inductions. Handrails were erected at the survey station to continue the focus on staff safety.
The risk assesments and method statements are in place for all activities such as the excavating and blinding around piles for the FST tanks and the pipework to the FST tanks.
It has been decided that in order to place an adequate focus on the environment and recycling that all waste should be segregated to minimise wastage and so that it can be sent to the correct depot.

Thursday 1 March 2007

Introduction to the Scheme

Brief scope of the works:

Design and build for the conversion of the existing SBR process to an extended activated sludge plant (ASP), associated new structures and all necessary activities to full integrate the new treatment process into the existing operations on site, comprising of:

  • Modification of existing SBR transfer pumping station
  • Selector Rank
  • SBR conversion
  • Final settlement tanks (FST's), RAS/SAS pumping station and additional SAS storage
  • Interconnecting process pipe work and wash water system
  • Control building and power supply infrastructure
  • Decommissioning of Works No. 3