Brief scope of the works:

Design and build for the conversion of the existing SBR process to an extended activated sludge plant (ASP), associated new structures and all necessary activities to full integrate the new treatment process into the existing operations on site, comprising of:

  • Modification of existing SBR transfer pumping station
  • Selector Rank
  • SBR conversion
  • Final settlement tanks (FST's), RAS/SAS pumping station and additional SAS storage
  • Interconnecting process pipe work and wash water system
  • Control building and power supply infrastructure
  • Decommissioning of Works No. 3